Facilities Stewardship: Demolition
Demolition of three district-owned residential buildings will occur during the summer of 2026. Removal of unused structures reduces utility and maintenance costs and improves safety. The two residential buildings across from West Linn High School are located on land that is targeted for additional parking as part of the bond program. The CREST program has relocated to the Stafford Campus, which is central to the District and in better physical condition.
The project is in design, with demolition expected this fall. Abatement work to begin in the coming days. Abatement is
performed by certified professionals with professional third party monitoring as required.
Recent Activities:
- Abatement and environmental services reports
- Permit drawings
- Procurement for abatement contractors
Upcoming Activities:
- Permit applications
- Select District-commissioned artwork to be preserved and stored
- Abatement work