Projects By School

Bond Program Summary (as of July 15, 2026)

  • Program launch is well underway
  • $5,051,968.64, or more than 2.4%, of total funds have been spent.
  • $14,136,289.64, or more than 6.8%, of total funds have been committed.
  • OSCIM Grant agreement has been approved by the School Board for more than $6.12 million of upgrades at Wood Middle School
  • The District issued (sold) nearly $130 million in bonds in April 2026, and experienced over $10.2 million in premium. Initial investments are expected to generate around $800,000.00 in interest.
  • Bond issuers (such as the District) need to commit 5% of issued bonds within 6 months of issuance. Commitments exceed 10% after only 3 months.
  • Summer 2026 projects are underway and on schedule
  • Summer 2027 projects are preparing to enter the design phase
  • The program schedule is in development, with expected review at the October Bond Oversight Committee meeting.

2025 Capital Bond Projects will be added to the appropriate level webpage as they are planned, contracted, and started across district schools. Projects are color coded by theme. 

  • Light Blue: Accessible Facilities
  • Green: Athletics and Wellness
  • Red: Facilities Stewardship
  • Yellow: Learning with Technology
  • Orange: Safe and Welcoming Schools
  • Dark Blue: STEAM, CTE, and Career Pathways
  • Purple: Sustainable and Resilient Facilities