WLHS Stadium and Parking Expansion
Recent Activities:
■ Project is Complete
Recent Activities:
- Concrete work occurred over winter break and will continue as weather allows
Upcoming Activities:
- Completion of concrete work
Recent Activities:
■ Final occupancy from the City of West Linn was received
■. The stadium is open and being used for events
■ The new AV system is fully functioning and being utilized for events
Upcoming Activities:
■ Concrete punch list items are expected to be completed during winter break
See the latest work being done at West Linn High School that is expanding and improving the stadium as well as building a new parking lot with nearly 100 new spaces for students this school year.
Recent Activities:
■ The new parking lot opened for use at the end of May
■ All landscaping and bark installation is complete
■ Concrete ramps were completed and opened for use in the Spring
■ The concessions area has been completed and open for use
■ The final concrete sections are completed as the contractor continues to work through the punch list
■ The contractor is completing handrail installation at the ramps
Upcoming Activities:
■ Final handrail installation and project closeout