WHS Performing Arts Center
To receive project updates for the Wilsonville High Performing Arts Center, sign up for the WLWV-Bond-WHS-Performing-Arts-Center ListServ.
Recent Activities:
■ Project is substantially complete
■ Contractor punch work items being addressed
■ Exterior building signage at north entry is complete
Upcoming Activities:
■ Project closeout
■ Installation of exterior building signage on south entry
■ Additional mechanical screen wall work
Join Us for the Dedication of the Wilsonville High School Performing Arts Center
The entire community is invited to the Wilsonville High School Performing Arts Center Dedication Ceremony on November 13 starting at 7 p.m.; 6880 SW Wilsonville Road.
The event will include an official ribbon cutting ceremony and student-led tours of the new building.
Recent Activities:
■ Phase 4, which includes the Black Box and old theater conversion to CTE spaces are nearing completion
■ Required firewall work is complete
■ The technology hub is being used by the school
■ Roof repairs are complete with flashing work nearing completion
■ Final site plantings are complete
■ Contractor punch work items being addressed
Upcoming Activities:
■ Contractor punch list items continue
■ Installation of exterior building signage
■ Additional mechanical screen wall work
Tour the brand-new Performing Arts Center at Wilsonville High School. Check out the massive stage, impressive lighting, and behind the scenes working spaces that will help our students get a jump start on their dreams of turning the passion of theater into a career.
Recent Activities:
■ Phase 4 is underway, which includes the Black Box and old theater conversion to CTE spaces
■ Old auditorium in-fill is complete and structural work is underway
■ Theater rigging sytems inspections have been completed
■ Required firewall work is currently underway
■ Electrical rough in has started in teh new CTE spaces
■ Final accoustical treatments have been installed
■ Roof repairs have begun
■ Final site plantings are underway
Upcoming Activities:
■ Mechanical rough-in in the CTE space
■ Stud framing work to begin on the new interior walls for the new CTE and Black Box spaces
■ Installation of exterior building signage
■ Additional mechanical screen wall work
■ Existing exterior wall corrective work
■ Final site work