Project Updates
Recent Activities:
- Project is complete
Recent Activities:
■ Project has reached substantial completion and is in closeout
■ Furniture has arrived and is in use by the school
■ Wall graphics installed
■ Gym floor refinished and new bleachers installed
■ ADA Ramp to the athletic field and track is complete
Upcoming Activities:
■ Contractor punch list closeout items nearing completion
Recent Actitives:
■ Final phase of conversion from Athey Creek Middle School to Riverside High School has begun
■ Athey Creek materials have been removed from the building
■ Demolition and site work is underway in the new CTE classroom spaces and outside the building
■ Gym bleachers have been removed and salvaged for materials
■ Furniture for the new Student Services Hub space has been delivered and assembled
Upcoming Activities:
■ Installation fo new gym bleachers, restriping and refinishing the gym floor to occur in August
■ Rough-in of mechanical, electrical and plumbing in the CTE spaces
■ Updating the library space with acoustical panels, paint and circulation desk
New library, lobby, commons and select classroom furniture will arrive late July and early August
Recent Activities:
■ Office remodel punchlist work is 99% complete
■ The renovation for summer 2323 work to convert spaces to the new high school has been bid and a contract has been awarded.
■ Partial furniture orders placed for the new high school spaces
Upcoming Activities:
■ Office remodel final punchlist items to be complete
■ Empty current athy Creek Middle School and begin renovation summer 2023 for the school fall 2023.
■ Continue to order equipment, furniture and supplies for Riverside High School.