Skip To Main Content

Project Updates

Trillium entry
Trillium entry under construction
Maker space
IMG_6540
Wood Bathrooms
Willamette Entry
Wood exterior construction
Willamette7-15-21
Wood Exterior Construction
Wood Interior
Wood Interior
Wood 7-21
Willamette Rendering
WHS Lights
WHS Lights3
Athey track
Rosemont entry
P1400667
Boones Ferry Entry
P1400883
Boones Ferry Entry
P1410376
Cedaroak Park Entry
P1410622
Cedaroak Park Entry
P1400819
Rosemont Ridge Entry
P1410614
Rosemont Ridge Entry
P1400998
Rosemont Ridge Entry
P1410629
Stafford Entry
Wood

19029.007 – Boiler Replacement at Boones Ferry Primary School

Recent Activities:
■ The boilers have been installed and are awaiting commissioning. Temporary heating measures are in place until commissioning completes in October

19061.020 – Rewiring at Willamette Primary School

Recent Activities:
■ Project is complete


19063.001 – Security Hardware at West Linn High School

Recent Activities:
■ The project is substantially complete. Final review of hardware locations is underway.


19064.021 – Track Replacement at Rosemont Ridge Middle School
Recent Activities:
■ Project is complete, track is open

 

19029.007 – Boiler Replacement at Boones Ferry Primary School

Recent Activities:
■    The mechanical contractor started demo of the old boilers once school released for the summer
■    New piping is currently being fabricated in preparation for the arrival of the new boilers at the end of July
■    The building is fully functional while construction is underway

 

19061.020 – Rewiring at Willamette Primary School

Recent Activities:
■    Demolition of the existing wiring began once school released for the summer
■    The school is closed as work continues rewiring. The project is expected to be complete prior to the start of school

 

19063.001 – Security Hardware at West Linn High School

Recent Activities:
■    New hardware has been delivered to the school and electrical work is being completed prior to hardware instal-lation
■    The district is working with the contractor to re-key the entire building

 

19064.021 – Track Replacement at Rosemont Ridge Middle School

Recent Activities:
■    Demolition of the existing track began after the Memorial Day Holiday.
■    The track closed for the month of June to allow for replacement and striping
■    Work is complete and contractor is removing fencing to allow for community use in July

19029.007 – Boiler Replacement at Boones Ferry Primary School
Project Status: This project includes replacing the aging boilers with new energy-efficient boilers.


Recent Activities:
■    Project work will occur during the summer

 

19061.020 – Rewiring at Willamette Primary School
Project Status: This project includes replacing all network cabling and relocating wiring closets.


Recent Activities:
■    Project bids were received
■    Board approval was given for the low bidder, First Cascade Corp
■    Project work will occur during the summer

 

19063.001 – Security Hardware at West Linn High School
Project Status: This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.


Recent Activities:
■    Project bids were received
■    Board approval was given for the low bidder, Ross Builders Northwest LLC
■    Project work will occur during the summer

 

19064.021 – Track Replacement at Rosemont Ridge Middle School
Project Status: This project includes track resurfacing at Rosemont Ridge Middle School.


Recent Activities:
■    Board approval was given to Beynon Sports
■    Project work will occur during the summer

19029.007 – Boiler Replacement at Boones Ferry Primary School


Project Status: This project includes replacing the aging boilers with new energy efficient boilers.


Recent Activities:
■    Project bids were received.
■    Board approval was given for the low bidder Copper Mechanical to proceed
■    Contract is out for signature

 

19061.020 – Rewiring at Willamette Primary School
Project Status: This project includes replacing all network cabling and relocating wiring closets.


Recent Activities:
■    Project is out to bid. Bids are due January 11th.

19063.001 – Security Hardware at West Linn High School


Project Status: This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.


Recent Activities:
■    Project is out to bid. Bids are due January 24th.

 

19064.021 – Track Replacement at Rosemont Ridge Middle School

 Project Status: This project includes track resurfacing at Rosemont Ridge Middle School.


Recent Activities:
■    Project is in review and preparing for pricing

 

19039.018 – Security Upgrades at Trillium Creek Primary School
Project Status:
This project includes creating a secure entry vestibule and improved classroom lockdown capability.
Recent Activities:
■     Project has reached substantial completion and is in closeout

19059.009 – Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools Project Status:
This project includes security curtains and improved classroom lockdown capabilities at these three schools.
Recent Activities:
■     Project has reached substantial completion and is in closeout

9029.007 – Boiler Replacement at Boones Ferry Primary School Project Status:
This project includes replacing the aging boilers with new energy efficient boilers.
Recent Activities:
■     Project is in review and preparing to bid

19061.020 – Rewiring at Willamette Primary School
Project Status:
This project includes replacing all network cabling and relocating wiring closets.
Recent Activities:
■     Project is in review and preparing to bid

19063.001 – Security Hardware at West Linn High School
Project Status:
This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.
Recent Activities:
■     Project is in review and preparing to bid

19064.021 – Track Replacement at Rosemont Ridge Middle School Project Status:
This project includes track resurfacing at Rosemont Ridge Middle School.
Recent Activities:
■     Project is in review and preparing to bid