Project Updates
19029.007 – Boiler Replacement at Boones Ferry Primary School
Recent Activities:
■ The boilers have been installed and are awaiting commissioning. Temporary heating measures are in place until commissioning completes in October
19061.020 – Rewiring at Willamette Primary School
Recent Activities:
■ Project is complete
19063.001 – Security Hardware at West Linn High School
Recent Activities:
■ The project is substantially complete. Final review of hardware locations is underway.
19064.021 – Track Replacement at Rosemont Ridge Middle School
Recent Activities:
■ Project is complete, track is open
19029.007 – Boiler Replacement at Boones Ferry Primary School
Recent Activities:
■ The mechanical contractor started demo of the old boilers once school released for the summer
■ New piping is currently being fabricated in preparation for the arrival of the new boilers at the end of July
■ The building is fully functional while construction is underway
19061.020 – Rewiring at Willamette Primary School
Recent Activities:
■ Demolition of the existing wiring began once school released for the summer
■ The school is closed as work continues rewiring. The project is expected to be complete prior to the start of school
19063.001 – Security Hardware at West Linn High School
Recent Activities:
■ New hardware has been delivered to the school and electrical work is being completed prior to hardware instal-lation
■ The district is working with the contractor to re-key the entire building
19064.021 – Track Replacement at Rosemont Ridge Middle School
Recent Activities:
■ Demolition of the existing track began after the Memorial Day Holiday.
■ The track closed for the month of June to allow for replacement and striping
■ Work is complete and contractor is removing fencing to allow for community use in July
19029.007 – Boiler Replacement at Boones Ferry Primary School
Project Status: This project includes replacing the aging boilers with new energy-efficient boilers.
Recent Activities:
■ Project work will occur during the summer
19061.020 – Rewiring at Willamette Primary School
Project Status: This project includes replacing all network cabling and relocating wiring closets.
Recent Activities:
■ Project bids were received
■ Board approval was given for the low bidder, First Cascade Corp
■ Project work will occur during the summer
19063.001 – Security Hardware at West Linn High School
Project Status: This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.
Recent Activities:
■ Project bids were received
■ Board approval was given for the low bidder, Ross Builders Northwest LLC
■ Project work will occur during the summer
19064.021 – Track Replacement at Rosemont Ridge Middle School
Project Status: This project includes track resurfacing at Rosemont Ridge Middle School.
Recent Activities:
■ Board approval was given to Beynon Sports
■ Project work will occur during the summer
19029.007 – Boiler Replacement at Boones Ferry Primary School
Project Status: This project includes replacing the aging boilers with new energy efficient boilers.
Recent Activities:
■ Project bids were received.
■ Board approval was given for the low bidder Copper Mechanical to proceed
■ Contract is out for signature
19061.020 – Rewiring at Willamette Primary School
Project Status: This project includes replacing all network cabling and relocating wiring closets.
Recent Activities:
■ Project is out to bid. Bids are due January 11th.
19063.001 – Security Hardware at West Linn High School
Project Status: This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.
Recent Activities:
■ Project is out to bid. Bids are due January 24th.
19064.021 – Track Replacement at Rosemont Ridge Middle School
Project Status: This project includes track resurfacing at Rosemont Ridge Middle School.
Recent Activities:
■ Project is in review and preparing for pricing
19039.018 – Security Upgrades at Trillium Creek Primary School
Project Status:
This project includes creating a secure entry vestibule and improved classroom lockdown capability.
Recent Activities:
■ Project has reached substantial completion and is in closeout
19059.009 – Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools Project Status:
This project includes security curtains and improved classroom lockdown capabilities at these three schools.
Recent Activities:
■ Project has reached substantial completion and is in closeout
9029.007 – Boiler Replacement at Boones Ferry Primary School Project Status:
This project includes replacing the aging boilers with new energy efficient boilers.
Recent Activities:
■ Project is in review and preparing to bid
19061.020 – Rewiring at Willamette Primary School
Project Status:
This project includes replacing all network cabling and relocating wiring closets.
Recent Activities:
■ Project is in review and preparing to bid
19063.001 – Security Hardware at West Linn High School
Project Status:
This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.
Recent Activities:
■ Project is in review and preparing to bid
19064.021 – Track Replacement at Rosemont Ridge Middle School Project Status:
This project includes track resurfacing at Rosemont Ridge Middle School.
Recent Activities:
■ Project is in review and preparing to bid