Project Summary
Wilsonville High School opened in 1995 with 400 students in three grades. In January 2006, the district completed a major remodel and expansion of the facility, doubling the capacity of the school. By 2008-2009, enrollment had grown to over 1000 students. As part of the 2008 bond, Wilsonville High will receive refinished gym floors, a resurfaced track, stainless steel column wraps, HVAC in the locker rooms, new water heaters and reserve tanks in the boiler room, a re-lamped and revised lighting system in the stadium and baseball fields, turf on the softball field, and a storage building at the tennis courts. These upgrades will continue to build the reputation Wilsonville High School has earned over the past 15 years as one of the top high schools in Oregon.
Legend:
Project Tasks
- Athletic Field Improvements
- Football/Athletic Field
- 09061.019 Bird Netting Project Completion Report
Scheduled Completion Date: 2009-08-13 Project Manager: Remo Douglas
- 09061.019 Bird Netting Project Completion Report
- Tennis Courts
- 09066.019 -Tennis Improvement Project Includes all projects below
- 09066.019 Add 2 Tennis Court
- 09066.019 Add New Storage Building Project Completion Report
Scheduled Completion Date: 2011-02-02 Project Manager: Remo Douglas - 09066.019 Install Bleachers
- 09066.019 Tennis Court Lights
- Womens Softball Field
- 09016.009 -Softball Improvements Project Completion Report
Scheduled Completion Date: 2010-02-20 Project Manager: Remo Douglas - 09016.009 Field Drainage Project Completion Report
- 09016.009 New All-Weather Turf Project Completion Report
- 09016.009 -Softball Improvements Project Completion Report
- Football/Athletic Field
- Deferred Maintenance
- Architectural
- 09003.009 Refinish Gym Floors @ Bolton, Boeckman, Wood, Wilsonville High & Willamette Project Completion Report
Scheduled Completion Date: 2009-11-11 Project Manager: Bob Teters - 09007.019 Auditorium/Gym Finishes/Wall Pads Project Completion Report
Scheduled Completion Date: 2009-03-18 Project Manager: Remo Douglas - 09011.009 Stainless Steel Column Wraps @ West Linn High & Wilsonville High Project Completion Report
Scheduled Completion Date: 2009-09-11 Project Manager: Operations
- 09003.009 Refinish Gym Floors @ Bolton, Boeckman, Wood, Wilsonville High & Willamette Project Completion Report
- Mechanical
- 09020.009 -Mechanical-Electrical Upgrades @ Athey, Rosemont & Wilsonville High Project Completion Report
Scheduled Completion Date: 2009-10-22 Project Manager: Bob Teters
- 09020.009 -Mechanical-Electrical Upgrades @ Athey, Rosemont & Wilsonville High Project Completion Report
- Mechanical - the projects listed below are included in the major project above:
- 09020.009 Add HVAC unit in locker rooms
- 09020.009 Energy Efficient HVAC Replacement/Improvement
- 09020.009 Replace AHU Drives with VFD
- 09020.009 Replace Water Heaters and Reserve Tank in Boiler Room
- Site
- 09008.009 Track Resurfacing Project @ West Linn High, Wilsonville High Project Completion Report
Scheduled Completion Date: 2009-09-18 Project Manager: Remo Douglas - 09024.019 Athletic Field Lighting Revisions Project Completion Report
Scheduled Completion Date: 2010-08-20 Project Manager: Remo Douglas
- 09008.009 Track Resurfacing Project @ West Linn High, Wilsonville High Project Completion Report
- Architectural
- Technology
-
- 09057.009 -Technology Improvements Districtwide Includes all projects listed below
- 09057.009 Building Communication Systems
- 09057.009 Computer Hardware/Software
-
Project Documents
Click to save or open a document
- 03-04-2009-Sports Facilities Meeting Minutes
- 03-24-2009-Softball Fields Meeting Minutes
- 9-15-2009 Sotball Project Meeting Minutes
- 10-20-2009 Softball Project Meeting Minutes
- 03-31-2009-Auditorium and Drama Dept Meeting Minutes
- 07-01-2009 Auditorium & Gym Finishes Meeting Minutes
- 07-08-2009 Auditorium & Gym Finishes Meeting Minutes
- 07-14-2009 Auditorium & Gym Finishes Meeting Minutes
- 07-21-2009 Auditorium & Gym Finishes Meeting Minutes
- 07-28-2009 Auditorium & Gym Finishes Meeting Minutes
- 08-04-2009 Auditorium & Gym Finishes Meeting Minutes
- 08-11-2009 Auditorium & Gym Finishes Meeting Minutes
- 08-19-2009 Auditorium & Gym Finishes Meeting Minutes
- 09-08-2009 Auditorium & Gym Finishes Meeting Minutes
- 8-16-2010 Tennis Storage Building Pre-Construction Notes
- 8-23-2010 Tennis Storage Building Meeting Notes
- 9-13-2010 Tennis Storage Building Meeting Notes
- 9-20-2010 Tennis Storage Building Meeting Notes
- Bid Award for Wilsonville High Gym & Auditorium Finishes
- Bid Award for Athey Creek Mechanical-Electrical Upgrades
- 04-01-2009-Softball Fields Meeting Minutes
- 07-07-2009 Mechanical Electrical Project Meeting Minutes
- 07-14-2009 Mechanical Electrical Project Meeting Minutes
- 07-21-2009 Mechanical Electrical Project Meeting Minutes
- 07-28-2009 Mechanical Electrical Project Meeting Minutes
- 08-04-2009 Mechanical Electrical Project Meeting Minutes
- 08-11-2009 Mechanical Electrical Project Meeting Minutes
- 08-18-2009 Mechanical Electrical Project Meeting Minutes
- 08-25-2009 Mechanical Electrical Project Meeting Minutes
- 09-01-2009 Mechanical Electrical Project Meeting Minutes
- 09-08-2009 Mechanical Electrical Project Meeting Minutes
- 09-15-2009 Mechanical Electrical Project Meeting Minutes
- 09-22-2009 Mechanical Electrical Project Meeting Minutes
- 9-29-2009 Mechanical Electrical Project Meeting Minutes
- 11-09-2009 Mechanical Electrical Project Meeting Minutes
- School Board Resolution Mechanical Electrical Projects
- 10-27-2009 Sotball Project Meeting Minutes
- Wilsonville Weekly Prinicipal email to Parent/Guardian 9/10/2009
View Wilsonville High School Website