2014 Capital Bond Program

Meridian Creek Middle School
Click Here to receive updates about the new Middle School in Wilsonville! 
 
6300 SW Hazel St, Wilsonville, OR 97070 
 
District Project Manager: Tony Vandenberg 503-673-7990
 
 
  • Meridian Creek Construction Weekend Work

    Posted by Amy Berger at 3/10/2017

    Dear West Linn-Wilsonville School District Subscriber,

     

    Capital Bond News:

    Meridian Creek Middle School

    Aerial North

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, March 11, 2017. Work will include building framing, roofing, and interior mechanical rough in.

    Due to weather sensitive roof installation, the Contactor may be working on Sunday March 12, 2017.

    The contractor continues with progress on site including:

    • Wall framing for the commons wing.
    • Installation of Weather barrier
    • Masonry
    • Siding

    During the week of March 13, the Contractor will continue building framing, plumbing rough-in, electrical rough-in, masonry, siding, and weather barrier.

    Right of Way Project

    During the week of March 13, work in the ROW will include overhead power relocation, and franchise utilities relocation. Flaggers will be present and short delays should be anticipated during working hours.  

    If you have any questions, please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Construction Update

    Posted by Amy Berger at 3/2/2017

    Dear West Linn-Wilsonville School District Subscriber,

     

    Capital Bond News:

    Meridian Creek Middle School

    North Drive

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, March 4, 2017. Work will include building framing and roofing.

    During the week of March 6, the Contractor will continue building framing, plumbing rough-in, electrical rough-in, masonry, and weather barrier.

    Right of Way Project

    During the week of March 6, work in the ROW will include overhead power pole relocation. A number of franchise utilities may be working to relocate utility lines. Flaggers will be present and short delays should be anticipated during working hours.  

    If you have any questions, please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Middle School - Right Of Way Construction Update

    Posted by Amy Berger at 2/10/2017

    Dear West Linn-Wilsonville School District Subscriber,

    Capital Bond News: Meridian Creek Middle School

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, February 11, 2017. Work will include building framing.

    The contractor continues with progress on site including:

    • Wall framing for the gym area, band and choir and classroom wing.
    • Installation of Weather barrier
    • Masonry

    During the week of February 13, the Contractor will continue building framing, plumbing rough-in, electrical rough-in, masonry, and weather barrier.

     

    Right of Way Project

    During the week of February 13, work in the ROW will include tree and vegetation removal primarily along Advance road. A number of franchise utilities may be working to relocate utility lines. Flaggers will be present and short delays should be anticipated during working hours.  

     

    If you have any questions, please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Construction Update

    Posted by Amy Berger at 1/27/2017

    Dear West Linn-Wilsonville School District Subscriber,

    Capital Bond News:

    Meridian Creek Middle School

    Public Improvements

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, January 28, 2017. Work will include building framing.

    The contractor continues with progress on site including:

    • Wall framing for the gym area, band and choir and classroom wing.

    During the week of January 30, the Contractor will continue building framing, plumbing rough-in, and electrical rough-in.

    Right of Way Project

    Work has started on the right of way project. This project includes improvements to roadways along Advance Road, Boeckman Road, new 63rd Avenue, new Hazel Street, and a signalized intersection located at Wilsonville Road/Stafford Rd/Boeckman Rd/Advance Rd. See the exhibit above.

    During the week of January 30, the contractor will continue surveying activities. NW Natural will be installing gas line along Advance Road.

    If you have any questions, please contact the Project Manager.

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Middle School Construction Update

    Posted by Amy Berger at 10/28/2016

    Dear West Linn-Wilsonville School District Subscriber,

    Capital Bond News: Meridian Creek Middle School

    Northeast View

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, October 29, 2016. Work will include general site work activities and building framing.

    The contractor continues with progress on site including:

    • Installation of site utilities.
    • Wall framing for the gym areas.

    The contractor will be installing site lighting for security purposes.

     

    If you have any questions, please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Construction Update

    Posted by Amy Berger at 10/5/2016

    Dear West Linn-Wilsonville School District Subscriber,

    Capital Bond News: Meridian Creek Middle School

    Meridian Construction Ariel

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, October 8, 2016. Work will include general site work activities and concrete.

    The contractor continues with progress on site including:

    • General site excavation and installation of site utilities.
    • Storm outfall construction is in progress.
    • Building floor slab preparation and placement.
    • Underground utilities.
    • Track curb placement and track base installation.
    • The contractor has started wall framing activities.

    During the Month of October anticipated activities include:

    • Wall framing for the gym areas and classroom areas.
    • Site utility installation.

    If you have any questions please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Construction Updates - Early Start Times

    Posted by Amy Berger at 8/18/2016

    Meridian Construction Ariel

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, August 20, 2016.

    Due to the extreme heat in the coming days, the contractor received approval from the city to start early on Friday August 19 and Monday August 22. Start time on Friday will be 6 AM and on Monday Start time will be 5 AM.

    If you have any questions please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Construction Update of Upcoming Activities

    Posted by Amy Berger at 7/25/2016

     During the month of August, Construction activities at the new Meridian Creek Middle School site will consist of the following:

    General Site Work:

    • General site excavation and fencing
    • Construction of building footings and foundations
    • Building utility placement

    Advance Road Work: The Contractor has completed work on Advance Road and for the next couple months only minor explorations are anticipated.

    Upcoming Work: During the next few months the contractor will focus on placement of building utilities, footings and foundations.

    If you have any questions please contact the Project Manager

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager - Amy Berger

    www.bond.wlwv.k12.or.us

    Comments (-1)
  • Meridian Creek Construction Update

    Posted by Amy Berger at 5/24/2016

    During the last week of May, Construction activities at the new Meridian Creek Middle School site will consist of the following:

    General Site Work:

    • Continue general site excavation
    • Excavation for the building pad
    • Construction of the new 63rd Avenue

    Advance Road Work: The Contractor will continue installing utilities on Advance Rd toward the site and flaggers will be visible. Drivers should anticipate some delays. The contractor is concentrating on this area to complete work and reduce traffic impacts. The utilities installation on Advance Rd is anticipated to be completed in the next two weeks.

    Upcoming Work: During the month of June the contractor will begin ground stabilization work in the area of the proposed building location.

    The Contractor will be working weekdays, and also Saturdays through June.

    If you have any questions please contact the Project Manager.

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    www.bond.wlwv.k12.or.us