School Logo

2014 Capital Bond Program

Meridian Creek Middle School
Click Here to receive updates about the new Middle School in Wilsonville! 
 
6300 SW Hazel St, Wilsonville, OR 97070 
 
District Project Manager: Tony Vandenberg 503-673-7990
 
 
  • Meridian Creek Construction Update

    Posted by Amy Berger at 4/20/2017

    Recent Activities:

    • The Right of Way project is well underway; the contractor continues work along Advance Road, 63rd Avenue and Hazel Street.
    • Robinson Construction has continued construction of the Middle School building.
    • Exterior finishes are proceeding.
    • Structure is nearly framed.
    • Interior finishes are in progress with sheetrock installation started in the gym and classroom wing.
    • Building electrical and plumbing rough-in continues throughout the building.
    • Bulk furnishings procurement is nearly complete.

    Upcoming Activities:

    • Paving of 63rd Avenue and Hazel Street
    • Road closure of Advance Road adjacent to the project and completion of paving and improvements to the Wilsonville/Stafford/Boeckman/Advance intersection
    • Siding and window installation starting at the gyms
    • Sheetrock and painting throughout the building
    • Mechanical and electrical equipment installation continuing
    • Site work including parking lot paving and site lighting
    Comments (-1)
  • Meridian Creek Construction Update

    Posted by Amy Berger at 4/14/2017

    Dear West Linn-Wilsonville School District Subscriber, 

    Capital Bond News: Meridian Creek Middle School

    North View

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, April 15, 2017. Work will include building interior mechanical and electrical work and also site work. Paving work on 63rd Avenue and Hazel Street will also occur this Saturday.

    The contractor continues with progress including:

    • Roofing for the commons wing.
    • Installation of Weather barrier, flashing, windows, and siding

    During the week of April 17, the Contractor will continue plumbing rough-in, electrical rough-in, insulation, sheetrock, masonry, siding, window installation, and weather barrier.

    Right of Way Project

    During the week of April 17, work in the ROW will include excavation for sanitary sewer in advance road and installation of storm water facilities. Flaggers will be present and short delays should be anticipated during working hours. Road closure on Advance Road will begin April 29, 2017 and will continue until May 29, 2017.

    If you have any questions, please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Construction Weekend Work

    Posted by Amy Berger at 3/10/2017

    Dear West Linn-Wilsonville School District Subscriber,

     

    Capital Bond News:

    Meridian Creek Middle School

    Aerial North

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, March 11, 2017. Work will include building framing, roofing, and interior mechanical rough in.

    Due to weather sensitive roof installation, the Contactor may be working on Sunday March 12, 2017.

    The contractor continues with progress on site including:

    • Wall framing for the commons wing.
    • Installation of Weather barrier
    • Masonry
    • Siding

    During the week of March 13, the Contractor will continue building framing, plumbing rough-in, electrical rough-in, masonry, siding, and weather barrier.

    Right of Way Project

    During the week of March 13, work in the ROW will include overhead power relocation, and franchise utilities relocation. Flaggers will be present and short delays should be anticipated during working hours.  

    If you have any questions, please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Construction Update

    Posted by Amy Berger at 3/2/2017

    Dear West Linn-Wilsonville School District Subscriber,

     

    Capital Bond News:

    Meridian Creek Middle School

    North Drive

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, March 4, 2017. Work will include building framing and roofing.

    During the week of March 6, the Contractor will continue building framing, plumbing rough-in, electrical rough-in, masonry, and weather barrier.

    Right of Way Project

    During the week of March 6, work in the ROW will include overhead power pole relocation. A number of franchise utilities may be working to relocate utility lines. Flaggers will be present and short delays should be anticipated during working hours.  

    If you have any questions, please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Middle School - Right Of Way Construction Update

    Posted by Amy Berger at 2/10/2017

    Dear West Linn-Wilsonville School District Subscriber,

    Capital Bond News: Meridian Creek Middle School

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, February 11, 2017. Work will include building framing.

    The contractor continues with progress on site including:

    • Wall framing for the gym area, band and choir and classroom wing.
    • Installation of Weather barrier
    • Masonry

    During the week of February 13, the Contractor will continue building framing, plumbing rough-in, electrical rough-in, masonry, and weather barrier.

     

    Right of Way Project

    During the week of February 13, work in the ROW will include tree and vegetation removal primarily along Advance road. A number of franchise utilities may be working to relocate utility lines. Flaggers will be present and short delays should be anticipated during working hours.  

     

    If you have any questions, please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Construction Update

    Posted by Amy Berger at 1/27/2017

    Dear West Linn-Wilsonville School District Subscriber,

    Capital Bond News:

    Meridian Creek Middle School

    Public Improvements

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, January 28, 2017. Work will include building framing.

    The contractor continues with progress on site including:

    • Wall framing for the gym area, band and choir and classroom wing.

    During the week of January 30, the Contractor will continue building framing, plumbing rough-in, and electrical rough-in.

    Right of Way Project

    Work has started on the right of way project. This project includes improvements to roadways along Advance Road, Boeckman Road, new 63rd Avenue, new Hazel Street, and a signalized intersection located at Wilsonville Road/Stafford Rd/Boeckman Rd/Advance Rd. See the exhibit above.

    During the week of January 30, the contractor will continue surveying activities. NW Natural will be installing gas line along Advance Road.

    If you have any questions, please contact the Project Manager.

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Construction Update

    Posted by Amy Berger at 1/20/2017

    Recent Activities:

    • The Right of Way easements and acquisitions associated with required Right of Way work have been complted.
    • Bids for the Public Improvements Project were received December 20, 2016. The low bidder was K&E Excavating Inc. The bids came in under the engineers estimated value.
    • Robinson Construction has continued construction of the Middle School building.
    • Concrete floor slab pours were completed.
    • Structure is proceeding with the main gym, auxiliary gym and band/choir areas nearly framed.
    • Framing of the classroom wing has started.
    • Building electrical and plumbing rough-in has started throughout the building and is following structure.

    Upcoming Activities:

    • Excavation and utilities installation along Advance Road.
    • Framing of the classroom wing and administration/commons.
    • FF&E Procurement.
    Comments (-1)
  • Meridian Creek Middle School Construction Update

    Posted by Amy Berger at 10/28/2016

    Dear West Linn-Wilsonville School District Subscriber,

    Capital Bond News: Meridian Creek Middle School

    Northeast View

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, October 29, 2016. Work will include general site work activities and building framing.

    The contractor continues with progress on site including:

    • Installation of site utilities.
    • Wall framing for the gym areas.

    The contractor will be installing site lighting for security purposes.

     

    If you have any questions, please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Meridian Creek Construction Update

    Posted by Amy Berger at 10/5/2016

    Dear West Linn-Wilsonville School District Subscriber,

    Capital Bond News: Meridian Creek Middle School

    Meridian Construction Ariel

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, October 8, 2016. Work will include general site work activities and concrete.

    The contractor continues with progress on site including:

    • General site excavation and installation of site utilities.
    • Storm outfall construction is in progress.
    • Building floor slab preparation and placement.
    • Underground utilities.
    • Track curb placement and track base installation.
    • The contractor has started wall framing activities.

    During the Month of October anticipated activities include:

    • Wall framing for the gym areas and classroom areas.
    • Site utility installation.

    If you have any questions please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • Construction Updates - Early Start Times

    Posted by Amy Berger at 8/18/2016

    Meridian Construction Ariel

    *SPECIAL NOTICE*

    The Contractor will be working on Saturday, August 20, 2016.

    Due to the extreme heat in the coming days, the contractor received approval from the city to start early on Friday August 19 and Monday August 22. Start time on Friday will be 6 AM and on Monday Start time will be 5 AM.

    If you have any questions please contact the Project Manager.

     

    Anthony Vandenberg

    vandenbt@wlwv.k12.or.us

    503-956-6406

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
CLOSE